December 9, 2014  ·  1 min read  ·  Materials

Holiday Inn Express 89-Key Guestroom FF&E & Casegoods Bid: North Houston

Coordinating an itemized 89-room guestroom FF&E package, fabric yardages, custom millwork details, and lighting counts for a North Houston Holiday Inn Express.

Holiday Inn Express 89-Key Guestroom FF&E & Casegoods Bid: North Houston

Midscale hotel renovations and buildouts stall on installation day when guestroom counts across floor plans do not match factory yardage and piece schedules. On an 89-key Holiday Inn Express project in North Houston, Texas during late 2014, we priced and balanced the full guestroom FF&E bill of materials across ten distinct room types.

Each category was broken down room by room so bedding, drapery, upholstery, lighting, and custom casegoods landed in exact building quantities rather than rough per-key multipliers.

Room Mix and Casegoods Balance

The takeoff tracked ten separate room configurations totaling 89 guestrooms:

  • Standard rooms: 45 King and 20 Double Queen units, alongside 1 ADA King and 3 ADA Double Queen rooms.
  • Suites: 10 standard King suites, 4 King-King suites, 3 King Executive suites, 1 ADA King suite, 1 King Jacuzzi suite, and 1 specialty suite.
  • Millwork counts: 70 laminated King headboards, 46 Queen headboards, 84 dressers with integrated TV wall panels, 5 accessible drawer chests, 89 desks, 89 end tables, and 89 luggage benches.

Separating accessible two-drawer chests from standard TV wall panels kept ADA clearances compliant without holding up standard-bay casegoods fabrication.

Fabrics, Lighting, and Soft Goods Yardage

Custom COM fabrics and electrical fixtures were quantified explicitly against each casegoods and seating piece:

  • Floor and wall finishes: 3,000 square yards of guestroom carpet, matching carpet pad, 7,000 linear feet of 4-inch base, and 1,800 square yards of headboard accent and bath wallcoverings.
  • Seating and drapery: 89 lounge chairs with matching ottomans, 89 desk chairs, 20 sleeper sofas for suite layouts, and 89 traversing blackout drapery assemblies with laminated cornices.
  • Lighting and mirrors: 140 King nightstand lamps, 23 Queen nightstand lamps, 89 floor lamps, 89 desk lamps, 20 oval suite table lamps, 178 vanity wall sconces, 89 full-length mirrors, and 89 vanity mirrors.

Specifying factory casegoods construction details alongside exact fixture quantities prevented shortage change orders during final guestroom installation.

More Holiday Inn Express projects

View all 28 Holiday Inn Express projects →